CompTIA
JK0-017 · Question #194
A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?
The correct answer is A. Communications Plan. See the full explanation below for the reasoning.
Question
A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?
Options
- ACommunications Plan
- BRisk Register
- CWork Breakdown Structure
- DChange Log
How the community answered
(55 responses)- A71% (39)
- B16% (9)
- C4% (2)
- D9% (5)
Community Discussion
No community discussion yet for this question.