nerdexam
CompTIA

JK0-017 · Question #193

The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?

The correct answer is B. Submit an RFQ to find a less expensive material. See the full explanation below for the reasoning.

Question

The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?

Options

  • AAsk the project sponsor to extend the project schedule.
  • BSubmit an RFQ to find a less expensive material.
  • CAssign additional team members to Quality Control.
  • DFast track the project to reduce risk.

How the community answered

(29 responses)
  • A
    10% (3)
  • B
    79% (23)
  • C
    7% (2)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice