CompTIA
JK0-017 · Question #193
The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?
The correct answer is B. Submit an RFQ to find a less expensive material. See the full explanation below for the reasoning.
Question
The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?
Options
- AAsk the project sponsor to extend the project schedule.
- BSubmit an RFQ to find a less expensive material.
- CAssign additional team members to Quality Control.
- DFast track the project to reduce risk.
How the community answered
(29 responses)- A10% (3)
- B79% (23)
- C7% (2)
- D3% (1)
Community Discussion