JK0-017 · Question #192
Which of the following is a goal of a kick-off meeting?
The correct answer is D. Relationship building between project team and stakeholders. See the full explanation below for the reasoning.
Question
Which of the following is a goal of a kick-off meeting?
Options
- AReview project progress with key stakeholders
- BGain customer acceptance of the deliverable
- CImplement an approved change request
- DRelationship building between project team and stakeholders
How the community answered
(61 responses)- A8% (5)
- B15% (9)
- C3% (2)
- D74% (45)