A project is having issues because the time required to do the smaller work items in the project were underestimated. This could have been avoided by using:
The correct answer is A. AWBS. See the full explanation below for the reasoning.
Question
A project is having issues because the time required to do the smaller work items in the project were underestimated. This could have been avoided by using:
Options
- AAWBS
- BQuality metrics
- CA scope statement
- DA budget
How the community answered
(16 responses)- A75% (12)
- B13% (2)
- C6% (1)
- D6% (1)