The project has spent $5,000 to date. The earned value of the project is $7,500. Using earned value management, which of the following is correct?
The correct answer is D. The project is under budget. See the full explanation below for the reasoning.
Question
The project has spent $5,000 to date. The earned value of the project is $7,500. Using earned value management, which of the following is correct?
Options
- AThe project is ahead of schedule.
- BThe project is over budget
- CThe project is behind schedule.
- DThe project is under budget.
How the community answered
(44 responses)- A5% (2)
- B14% (6)
- C7% (3)
- D75% (33)