Question

The project has spent $5,000 to date. The earned value of the project is $7,500. Using earned value management, which of the following is correct?

Options

  • AThe project is ahead of schedule.
  • BThe project is over budget
  • CThe project is behind schedule.
  • DThe project is under budget.