JK0-017 · Question #188

The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?

The correct answer is D. 1.5. See the full explanation below for the reasoning.

Question

The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?

Options

  • A-$2,500
  • B$12,500
  • C0.67
  • D1.5

How the community answered

(55 responses)
  • A
    13% (7)
  • B
    7% (4)
  • C
    4% (2)
  • D
    76% (42)