The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?
The correct answer is D. 1.5. See the full explanation below for the reasoning.
Question
The project has spent $5,000 to date. The earned value of the project is $7,500. Which of the following is the project's CPI?
Options
- A-$2,500
- B$12,500
- C0.67
- D1.5
How the community answered
(55 responses)- A13% (7)
- B7% (4)
- C4% (2)
- D76% (42)