In which of the following situations would a project manager conduct a post mortem?
The correct answer is A. The project sponsor stopped the project. See the full explanation below for the reasoning.
Question
In which of the following situations would a project manager conduct a post mortem?
Options
- AThe project sponsor stopped the project.
- BA key stakeholder is upset with the quality of a deliverable.
- CA new project manager has been assigned to the project.
- DTo determine why the change control board rejected a change request.
How the community answered
(43 responses)- A70% (30)
- B5% (2)
- C7% (3)
- D19% (8)