A project manager has received a written request to make a large change to one of the project deliverables. Which of the following would be the FIRST step taken after analyzing the impact?

The correct answer is C. Present the stakeholders with possible courses of action. See the full explanation below for the reasoning.

Question

A project manager has received a written request to make a large change to one of the project deliverables. Which of the following would be the FIRST step taken after analyzing the impact?

Options

  • ACrash the schedule to implement the change.
  • BUpdate the risk register with the appropriate change.
  • CPresent the stakeholders with possible courses of action.
  • DUpdate the appropriate project plan to reflect impact.

How the community answered

(63 responses)
  • A
    14% (9)
  • B
    3% (2)
  • C
    73% (46)
  • D
    10% (6)