Question

A project manager has received a written request to make a large change to one of the project deliverables. Which of the following would be the FIRST step taken after analyzing the impact?

Options

  • ACrash the schedule to implement the change.
  • BUpdate the risk register with the appropriate change.
  • CPresent the stakeholders with possible courses of action.
  • DUpdate the appropriate project plan to reflect impact.