Question
A project manager has received a written request to make a large change to one of the project deliverables. Which of the following would be the FIRST step taken after analyzing the impact?
Options
- ACrash the schedule to implement the change.
- BUpdate the risk register with the appropriate change.
- CPresent the stakeholders with possible courses of action.
- DUpdate the appropriate project plan to reflect impact.
Unlock JK0-017 to see the answer
You've previewed enough free JK0-017 questions. Unlock JK0-017 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.