To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?
The correct answer is A. PERT. See the full explanation below for the reasoning.
Question
To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?
Options
- APERT
- BGantt chart
- CWBS Dictionary
- DSPI
How the community answered
(25 responses)- A76% (19)
- B12% (3)
- C4% (1)
- D8% (2)