nerdexam
CompTIA

JK0-017 · Question #138

To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

The correct answer is A. PERT. See the full explanation below for the reasoning.

Question

To determine the MOST likely estimate for the length of project activities, a project manager would use which of the following?

Options

  • APERT
  • BGantt chart
  • CWBS Dictionary
  • DSPI

How the community answered

(25 responses)
  • A
    76% (19)
  • B
    12% (3)
  • C
    4% (1)
  • D
    8% (2)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice