A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a…

The correct answer is A. Time zones for various work locations. See the full explanation below for the reasoning.

Question

A project manager is working with a large team on an important project. Many of the team members work remotely. The project manager requires each team member to submit weekly status reports at a certain time each week. One team member consistently submits late status reports. Which of the following should the project manager consider FIRST?

Options

  • ATime zones for various work locations
  • BNecessity of weekly status reports
  • CFormat of the status report
  • DPast performance reviews of the team member

How the community answered

(27 responses)
  • A
    78% (21)
  • B
    4% (1)
  • C
    7% (2)
  • D
    11% (3)

Community Discussion