CompTIA
JK0-017 · Question #136
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the…
The correct answer is D. Crashing. See the full explanation below for the reasoning.
Question
A project manager added some experienced team members to work on certain project activities in conjunction with inexperienced team members because the project is behind schedule. Which of the following BEST describes the technique the project manager is using?
Options
- ASchedule optimization
- BFast tracking
- CResource management
- DCrashing
How the community answered
(29 responses)- A3% (1)
- B10% (3)
- C14% (4)
- D72% (21)
Community Discussion
No community discussion yet for this question.