JK0-017 · Question #140
As a project nears completion, the project manager finds out that several key members of the project team have been reassigned to other projects. If the scope and schedule of the project stay the…
The correct answer is A. Cost. See the full explanation below for the reasoning.
Question
As a project nears completion, the project manager finds out that several key members of the project team have been reassigned to other projects. If the scope and schedule of the project stay the same which of the following will change?
Options
- ACost
- BQuality metrics
- CKey Performance Indicators (KPIs)
- DWork performance
How the community answered
(46 responses)- A74% (34)
- B4% (2)
- C15% (7)
- D7% (3)