During project execution, the cost management plan would be used to:
The correct answer is D. determine if variances exceed a defined threshold. See the full explanation below for the reasoning.
Question
During project execution, the cost management plan would be used to:
Options
- Aensure that resources are compensated fairly.
- Bschedule resources for each phase of the project.
- Cidentify costs that were not previously identified.
- Ddetermine if variances exceed a defined threshold.
How the community answered
(41 responses)- A5% (2)
- B10% (4)
- C2% (1)
- D83% (34)