nerdexam
CompTIA

JK0-017 · Question #131

During project execution, the cost management plan would be used to:

The correct answer is D. determine if variances exceed a defined threshold. See the full explanation below for the reasoning.

Question

During project execution, the cost management plan would be used to:

Options

  • Aensure that resources are compensated fairly.
  • Bschedule resources for each phase of the project.
  • Cidentify costs that were not previously identified.
  • Ddetermine if variances exceed a defined threshold.

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    10% (4)
  • C
    2% (1)
  • D
    83% (34)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice