The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?

The correct answer is A. ETC. See the full explanation below for the reasoning.

Question

The project has an AC of $5,000. Which of the following would be used to determine the budget needed to complete the project?

Options

  • AETC
  • BPV
  • CBAC
  • DEAC

How the community answered

(43 responses)
  • A
    72% (31)
  • B
    5% (2)
  • C
    7% (3)
  • D
    16% (7)