A new project manager is beginning work on a high profile project with a budget of $3.2 million. The project manager has not spoken directly to the IT department regarding the necessary hardware for…

The correct answer is D. Assumptions. See the full explanation below for the reasoning.

Question

A new project manager is beginning work on a high profile project with a budget of $3.2 million. The project manager has not spoken directly to the IT department regarding the necessary hardware for this project. The project manager has determined, based on past experience, that it will not be necessary to purchase additional servers for the project. This is an example of which of the following?

Options

  • AConstraints
  • BStandards compliance
  • CAcceptance criteria
  • DAssumptions

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    15% (6)
  • C
    3% (1)
  • D
    78% (31)