JK0-017 · Question #127

The project manager will define a scale of probability from "unlikely" to "certain" in which of the following documents?

The correct answer is A. Risk management plan. See the full explanation below for the reasoning.

Question

The project manager will define a scale of probability from "unlikely" to "certain" in which of the following documents?

Options

  • ARisk management plan
  • BScope management plan
  • CQuality management plan
  • DSchedule management plan

How the community answered

(41 responses)
  • A
    71% (29)
  • B
    7% (3)
  • C
    5% (2)
  • D
    17% (7)