nerdexam
CompTIA

JK0-017 · Question #128

The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be…

The correct answer is A. Communication plan. See the full explanation below for the reasoning.

Question

The project is behind schedule. A project team member has analyzed the work performance information and has not created the weekly status update because they are uncertain when the update should be completed. Which of the following documents should the team member consult?

Options

  • ACommunication plan
  • BRisk plan
  • CScope plan
  • DQuality plan

How the community answered

(27 responses)
  • A
    85% (23)
  • B
    7% (2)
  • C
    4% (1)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice