A project has produced 2000 of the same deliverable. The project manager does not have time to inspect every deliverable, but would like some assurance the deliverables are meeting the…
The correct answer is C. Statistical sampling. See the full explanation below for the reasoning.
Question
A project has produced 2000 of the same deliverable. The project manager does not have time to inspect every deliverable, but would like some assurance the deliverables are meeting the specifications. Which of the following techniques should be used?
Options
- ADefect repair review
- BProcess analysis
- CStatistical sampling
- DDesign of experiments
How the community answered
(40 responses)- A15% (6)
- B3% (1)
- C75% (30)
- D8% (3)