nerdexam
CompTIA

JK0-017 · Question #119

A project team has determined that all status reports will be sent via email. Which of the following components of the project plan documents this information?

The correct answer is B. Communication plan. See the full explanation below for the reasoning.

Question

A project team has determined that all status reports will be sent via email. Which of the following components of the project plan documents this information?

Options

  • AStatus report plan
  • BCommunication plan
  • CDiscussion plan
  • DDecision log

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    75% (38)
  • C
    16% (8)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice