Which of the following project documents lists risks and describes the strategy to deal with a risk?

The correct answer is B. Risk register. See the full explanation below for the reasoning.

Question

Which of the following project documents lists risks and describes the strategy to deal with a risk?

Options

  • ARisk categorization
  • BRisk register
  • CRisk analysis
  • DRisk breakdown structure

How the community answered

(41 responses)
  • A
    20% (8)
  • B
    71% (29)
  • C
    7% (3)
  • D
    2% (1)