JK0-017 · Question #120

A project manager is reviewing the scope statement of a project. Which of the following project management plan components would define the measureable tasks of the project?

The correct answer is D. Project schedule. See the full explanation below for the reasoning.

Question

A project manager is reviewing the scope statement of a project. Which of the following project management plan components would define the measureable tasks of the project?

Options

  • AIssues log
  • BQuality metrics
  • CResource requirements
  • DProject schedule

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    4% (1)
  • C
    7% (2)
  • D
    85% (23)