Which of the following tools would a project manager use to determine the root cause of an issue?

The correct answer is B. Ishikawa Diagram. See the full explanation below for the reasoning.

Question

Which of the following tools would a project manager use to determine the root cause of an issue?

Options

  • APareto Chart
  • BIshikawa Diagram
  • CHistogram
  • DMonte Carlo Analysis

How the community answered

(17 responses)
  • B
    82% (14)
  • C
    12% (2)
  • D
    6% (1)