CompTIA
JK0-017 · Question #111
Which of the following tools would a project manager use to determine the root cause of an issue?
The correct answer is B. Ishikawa Diagram. See the full explanation below for the reasoning.
Question
Which of the following tools would a project manager use to determine the root cause of an issue?
Options
- APareto Chart
- BIshikawa Diagram
- CHistogram
- DMonte Carlo Analysis
How the community answered
(17 responses)- B82% (14)
- C12% (2)
- D6% (1)
Community Discussion