The project's network map has a loop with multiple project outcomes. This is the result of which of the following scheduling tools?
The correct answer is D. Graphical evaluation and review technique. See the full explanation below for the reasoning.
Question
The project's network map has a loop with multiple project outcomes. This is the result of which of the following scheduling tools?
Options
- AEstablishing project schedule baselines
- BCritical Path Analysis
- CCritical Chain Method
- DGraphical evaluation and review technique
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C4% (1)
- D81% (21)