Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
The correct answer is D. Precedence Diagramming Method. See the full explanation below for the reasoning.
Question
Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
Options
- ACritical Path Method
- BArrow Diagramming Method
- CCritical Chain Method
- DPrecedence Diagramming Method
How the community answered
(28 responses)- A14% (4)
- B7% (2)
- C4% (1)
- D75% (21)