Deming proposed a system of continuous improvement. Which four activities does this system involve?

The correct answer is A. Plan. Do. Check and Act. Option A is correct because Deming's system - known as the PDCA cycle - stands for Plan, Do, Check, and Act, the exact four phases he originally described for continuous improvement. Options B and D replace "Check" with "Evaluate," which is a plausible-sounding but incorrect subs

Basic concepts

Question

Deming proposed a system of continuous improvement. Which four activities does this system involve?

Options

  • APlan. Do. Check and Act
  • BPlan. Do. Evaluate and Act
  • CPlan. Perform. Audit and Improve
  • DPlan. Perform. Evaluate and Act

How the community answered

(48 responses)
  • A
    79% (38)
  • B
    13% (6)
  • C
    6% (3)
  • D
    2% (1)

Explanation

Option A is correct because Deming's system - known as the PDCA cycle - stands for Plan, Do, Check, and Act, the exact four phases he originally described for continuous improvement. Options B and D replace "Check" with "Evaluate," which is a plausible-sounding but incorrect substitution; Deming specifically used "Check" (later revised to "Study" in his updated model, but never "Evaluate"). Options C and D both swap "Do" for "Perform," which changes the original terminology without basis. A reliable memory tip: think of "PDCA = Please Don't Change Anything" - the first letters lock in Plan, Do, Check, Act in order, reminding you that the original wording must stay intact.

Topics

#Deming#PDCA cycle#continuous improvement#quality management