Deming proposed a system of continuous improvement. Which four activities does this system involve?
The correct answer is A. Plan. Do. Check and Act. Option A is correct because Deming's system - known as the PDCA cycle - stands for Plan, Do, Check, and Act, the exact four phases he originally described for continuous improvement. Options B and D replace "Check" with "Evaluate," which is a plausible-sounding but incorrect subs
Question
Deming proposed a system of continuous improvement. Which four activities does this system involve?
Options
- APlan. Do. Check and Act
- BPlan. Do. Evaluate and Act
- CPlan. Perform. Audit and Improve
- DPlan. Perform. Evaluate and Act
How the community answered
(48 responses)- A79% (38)
- B13% (6)
- C6% (3)
- D2% (1)
Explanation
Option A is correct because Deming's system - known as the PDCA cycle - stands for Plan, Do, Check, and Act, the exact four phases he originally described for continuous improvement. Options B and D replace "Check" with "Evaluate," which is a plausible-sounding but incorrect substitution; Deming specifically used "Check" (later revised to "Study" in his updated model, but never "Evaluate"). Options C and D both swap "Do" for "Perform," which changes the original terminology without basis. A reliable memory tip: think of "PDCA = Please Don't Change Anything" - the first letters lock in Plan, Do, Check, Act in order, reminding you that the original wording must stay intact.