Which processes should the Plan, Do, Check, Act methodology be applied to?
The correct answer is A. all of the processes within the scope. You've hit your weekly limit · resets 5am (America/New_York)
Planning and implementing service management
Question
Which processes should the Plan, Do, Check, Act methodology be applied to?
Options
- Aall of the processes within the scope
- Bthe Planning & Implementing Service Management process
- Cthe Requirements for a Management System process
- Dthose that support business critical services
How the community answered
(21 responses)- A81% (17)
- B5% (1)
- C10% (2)
- D5% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)