ITIL · Question #54
Which process is responsible for ensuring that appropriate testing takes place?
The correct answer is B. Release and deployment management. Release and deployment management owns the responsibility for planning, building, testing, and deploying releases into live environments.
Question
Which process is responsible for ensuring that appropriate testing takes place?
Options
- AKnowledge management
- BRelease and deployment management
- CService asset and configuration management
- DService level management
How the community answered
(25 responses)- A4% (1)
- B88% (22)
- D8% (2)
Why each option
Release and deployment management owns the responsibility for planning, building, testing, and deploying releases into live environments.
Knowledge management focuses on capturing, storing, and sharing information and knowledge across the organization, not testing.
Release and deployment management is explicitly responsible for ensuring that appropriate testing occurs before releases are deployed to production. It encompasses build, test, and deployment activities to verify that releases meet requirements and do not introduce unacceptable risk to live services.
Service asset and configuration management tracks and controls configuration items (CIs) and their relationships, not release testing.
Service level management negotiates, monitors, and reports on service level agreements, with no direct role in testing releases.
Concept tested: Release and deployment management testing responsibility
Source: https://learn.microsoft.com/en-us/azure/devops/learn/what-is-continuous-delivery