nerdexam
PeopleCert

ITIL · Question #411

A plan for managing the end of a supplier contract should be created when?

The correct answer is A. The contract is being negotiated. ITIL Supplier Management best practice requires that exit or end-of-contract plans be established at the time the contract is being negotiated, not after it is signed or nearing expiry.

Processes

Question

A plan for managing the end of a supplier contract should be created when?

Options

  • AThe contract is being negotiated
  • BThe contract is about to be ended
  • CThe Supplier Manager decides that there is a risk the contract might need to end soon
  • DThe contract has been agreed

How the community answered

(40 responses)
  • A
    73% (29)
  • B
    5% (2)
  • C
    15% (6)
  • D
    8% (3)

Why each option

ITIL Supplier Management best practice requires that exit or end-of-contract plans be established at the time the contract is being negotiated, not after it is signed or nearing expiry.

AThe contract is being negotiatedCorrect

Planning for contract termination during the negotiation phase ensures that exit clauses, data migration responsibilities, transition support, and continuity arrangements are formally captured and agreed upon before the contract is signed. This proactive approach protects the service provider and avoids scrambling for contingency plans when the relationship is already under strain. ITIL Supplier Management explicitly recommends that termination plans be part of initial contract design.

BThe contract is about to be ended

Waiting until the contract is about to end leaves insufficient time to negotiate transition terms, arrange alternative suppliers, or protect service continuity.

CThe Supplier Manager decides that there is a risk the contract might need to end soon

While risk awareness is valuable, waiting for the Supplier Manager to perceive a risk is reactive rather than the proactive stance ITIL requires for contract governance.

DThe contract has been agreed

Creating the plan only after the contract has been agreed means exit provisions may not be contractually enforceable, as they were not negotiated as part of the agreement.

Concept tested: ITIL Supplier Management exit planning timing

Source: https://www.axelos.com/certifications/itil-service-management

Topics

#supplier management#contract management#supplier contracts#risk management

Community Discussion

No community discussion yet for this question.

Full ITIL Practice