Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and…

The correct answer is A. 3-1-2-4. This question tests knowledge of how the PDCA (Plan-Do-Check-Act) cycle maps to Continual Service Improvement implementation steps in ITIL.

Key principles and models

Question

Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and responsibilities to work on CSI initiatives. (2) Measure and review that the CSI plan is executed and its objectives are being achieved. (3) Identify the scope, objectives and requirements for CSI. (4) Decision on implementation of further enhancement.

Options

  • A3-1-2-4
  • B3-4-2-1
  • C1-3-2-4
  • D2-3-4-1

How the community answered

(17 responses)
  • A
    82% (14)
  • C
    12% (2)
  • D
    6% (1)

Why each option

This question tests knowledge of how the PDCA (Plan-Do-Check-Act) cycle maps to Continual Service Improvement implementation steps in ITIL.

A3-1-2-4Correct

The correct sequence 3-1-2-4 maps directly to PDCA: step 3 (identify scope and objectives) is the Plan phase where goals are established; step 1 (allocate roles and responsibilities) is the Do phase where the plan is executed; step 2 (measure and review) is the Check phase where results are evaluated against objectives; step 4 (decision on further enhancement) is the Act phase where improvements are approved and the cycle continues.

B3-4-2-1

Sequence 3-4-2-1 places the decision on further enhancement before measuring results, which skips the Check phase and violates the PDCA order.

C1-3-2-4

Sequence 1-3-2-4 places role allocation before identifying scope and objectives, meaning execution begins before planning is complete, reversing Plan and Do.

D2-3-4-1

Sequence 2-3-4-1 starts with measuring, which is the Check phase, and places planning (step 3) second, fundamentally reversing the PDCA cycle.

Concept tested: PDCA cycle mapping to CSI implementation steps

Source: https://www.axelos.com/resource-hub/itil/itil-continual-service-improvement

Topics

#CSI#PDCA#Deming Cycle#continual improvement

Community Discussion

No community discussion yet for this question.