ITIL · Question #382

Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and responsibilities

Sign in or unlock ITIL to reveal the answer and full explanation for question #382. The question stem and answer options stay visible for context.

Key principles and models

Question

Order the following continual service improvement (CSI) implementation steps into the correct sequence in alignment with the plan, Do, Check, Act (PDCA) model. (1) Allocate roles and responsibilities to work on CSI initiatives. (2) Measure and review that the CSI plan is executed and its objectives are being achieved. (3) Identify the scope, objectives and requirements for CSI. (4) Decision on implementation of further enhancement.

Options

  • A3-1-2-4
  • B3-4-2-1
  • C1-3-2-4
  • D2-3-4-1

Unlock ITIL to see the answer

You've previewed enough free ITIL questions. Unlock ITIL for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#CSI#PDCA#Deming Cycle#continual improvement