Which one of the following is NOT an aim of the change management process?

The correct answer is D. To deliver and manage IT services at agreed levels to business users. Delivering and managing IT services at agreed levels is the aim of service level management, not change management.

Processes

Question

Which one of the following is NOT an aim of the change management process?

Options

  • ATo ensure the impact of changes are understood
  • BTo ensure that changes are recorded and evaluated
  • CTo ensure that all changes to configuration items (CIs) are recorded in the configuration management
  • DTo deliver and manage IT services at agreed levels to business users

How the community answered

(45 responses)
  • A
    4% (2)
  • B
    7% (3)
  • C
    18% (8)
  • D
    71% (32)

Why each option

Delivering and managing IT services at agreed levels is the aim of service level management, not change management.

ATo ensure the impact of changes are understood

Ensuring the impact of changes is understood is a genuine aim of change management, achieved through mandatory impact and risk assessment during change evaluation.

BTo ensure that changes are recorded and evaluated

Ensuring changes are recorded and evaluated is explicitly an aim of change management, fulfilled through the change request log and review by the change advisory board.

CTo ensure that all changes to configuration items (CIs) are recorded in the configuration management

Ensuring all changes to configuration items are recorded in configuration management is a key aim of change management, keeping the CMDB accurate and reflecting the current state of the IT infrastructure.

DTo deliver and manage IT services at agreed levels to business usersCorrect

Delivering and managing IT services at agreed levels to business users is a core objective of service level management (SLM), which defines, negotiates, and monitors service level agreements. Change management's aims are focused on controlling the lifecycle of changes to minimize risk and disruption, not on service delivery commitments. Including an SLM objective in change management would conflate two distinct ITIL processes with separate scopes and responsibilities.

Concept tested: Change management aims versus service level management

Source: https://www.axelos.com/best-practice-solutions/itil/itil-service-transition