nerdexam
PeopleCert

ITIL-FOUNDATION · Question #89

Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for comp

The correct answer is A. 1, 2 and 3 only. A change model must include steps, responsibilities, and timescales - complaints procedures are handled by separate service management processes and are not a component of a change model.

Know the purpose of the ITIL practices

Question

Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures

Options

  • A1, 2 and 3 only
  • BAll of the above
  • C1 and 3 only
  • D2 and 4 only

How the community answered

(37 responses)
  • A
    86% (32)
  • B
    3% (1)
  • C
    8% (3)
  • D
    3% (1)

Why each option

A change model must include steps, responsibilities, and timescales - complaints procedures are handled by separate service management processes and are not a component of a change model.

A1, 2 and 3 onlyCorrect

ITIL specifies that a change model must define the steps required to handle the change in a particular order, the responsibilities of who performs each step including escalation paths, and the timescales and thresholds for completing those actions. Complaints procedures are not part of a change model; they belong to separate governance or customer management processes, so item 4 is correctly excluded.

BAll of the above

Complaints procedures (item 4) are not a defined component of an ITIL change model, making inclusion of all four items incorrect.

C1 and 3 only

Responsibilities (item 2), including escalation, are a required element of a change model and cannot be omitted.

D2 and 4 only

Steps for handling the change (item 1) and timescales (item 3) are core required components of a change model, and complaints procedures (item 4) are not, making this combination incorrect.

Concept tested: ITIL change model required components

Source: https://www.axelos.com/certifications/itil-service-management/itil-4-foundation

Topics

#change management#change model#change process#escalation

Community Discussion

No community discussion yet for this question.

Full ITIL-FOUNDATION Practice