ITIL-FOUNDATION · Question #386
Which of the following activities is NOT a part of the Deming Cycle?
The correct answer is D. Coordinate. The Deming Cycle is a four-stage quality improvement model - Plan, Do, Check, Act. 'Coordinate' is not one of its stages.
Question
Which of the following activities is NOT a part of the Deming Cycle?
Options
- AAct
- BPlan
- CDo
- DCoordinate
How the community answered
(38 responses)- B5% (2)
- C3% (1)
- D92% (35)
Why each option
The Deming Cycle is a four-stage quality improvement model - Plan, Do, Check, Act. 'Coordinate' is not one of its stages.
Act is the fourth stage of the Deming Cycle, where results are reviewed and adjustments are standardized or the cycle is repeated.
Plan is the first stage of the Deming Cycle, where objectives and improvement processes are established.
Do is the second stage of the Deming Cycle, where the planned improvement is implemented on a small scale.
The Deming Cycle (PDCA) consists of exactly four stages: Plan, Do, Check, and Act. 'Coordinate' does not exist as a stage in this model, making it the item that is NOT part of the cycle.
Concept tested: Deming Cycle PDCA stages identification
Source: https://asq.org/quality-resources/pdca-cycle