ITIL-FOUNDATION · Question #378
When is it confirmed if a project's objectives have been achieved?
The correct answer is A. During the Closing a Project process. In PRINCE2, the Closing a Project process is the point at which the project's objectives are formally confirmed as achieved and the project is wound down.
Question
When is it confirmed if a project's objectives have been achieved?
Options
- ADuring the Closing a Project process
- BDuring the final end stage assessment
- CDuring the Controlling a Stage process
- DDuring the Managing Product Delivery process
How the community answered
(59 responses)- A95% (56)
- C2% (1)
- D3% (2)
Why each option
In PRINCE2, the Closing a Project process is the point at which the project's objectives are formally confirmed as achieved and the project is wound down.
The Closing a Project process is specifically designed to verify that the project's objectives have been met and that all products have been accepted by the customer. This process produces the End Project Report, which compares actual performance against the original Project Initiation Documentation to formally confirm whether objectives were achieved.
The final end stage assessment reviews the final stage's performance but does not formally confirm whether overall project objectives have been achieved - that confirmation occurs within Closing a Project.
Controlling a Stage manages day-to-day work within a stage, focusing on work package authorization and issue management, not confirming overall project objective achievement.
Managing Product Delivery is concerned with the delivery and acceptance of work packages by team managers, not with confirming that overall project objectives have been met.
Concept tested: PRINCE2 Closing a Project process purpose