A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

The correct answer is C. Budget. ISEB ISEB-PM1 Exam

Project Planning

Question

A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).

Options

  • AParametric
  • BBottom up.
  • CBudget
  • DTop down.
  • EDefinitive.

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    74% (40)
  • D
    13% (7)
  • E
    7% (4)

Explanation

ISEB ISEB-PM1 Exam

Topics

#budget estimate#estimate accuracy#cost estimation#estimate types