An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:
The correct answer is B. A dummy activity. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:
Options
- AA milestone
- BA dummy activity
- CBoth 1) A milestone and 2) A dummy activity
- DA hammock
How the community answered
(23 responses)- A9% (2)
- B83% (19)
- C4% (1)
- D4% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#dummy activity#network diagram#activity dependencies#precedence