An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:

The correct answer is B. A dummy activity. You've hit your weekly limit · resets 5am (America/New_York)

Project Planning

Question

An activity that consumes no time or resources and shows only that a dependency exists between two activities is called:

Options

  • AA milestone
  • BA dummy activity
  • CBoth 1) A milestone and 2) A dummy activity
  • DA hammock

How the community answered

(23 responses)
  • A
    9% (2)
  • B
    83% (19)
  • C
    4% (1)
  • D
    4% (1)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#dummy activity#network diagram#activity dependencies#precedence