ISEB-PM1 · Question #569
What is the standard deviation for the estimates in the above problem?
The correct answer is D. 0.6. You've hit your weekly limit · resets 5am (America/New_York)
Project Planning
Question
What is the standard deviation for the estimates in the above problem?
Options
- A2
- B0.5
- C1.5
- D0.6
How the community answered
(22 responses)- A14% (3)
- B5% (1)
- C5% (1)
- D77% (17)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#standard deviation#PERT estimation#three-point estimating#statistical analysis
Community Discussion
No community discussion yet for this question.