A summary WBS is usually developed in the

The correct answer is E. Conceptual phase. You've hit your weekly limit · resets 5am (America/New_York)

The Project Management Lifecycle

Question

A summary WBS is usually developed in the

Options

  • Aclose-out phase
  • BAll of the other alternatives apply phases
  • Cimplementation phase
  • Dplanning phase
  • EConceptual phase

How the community answered

(67 responses)
  • A
    1% (1)
  • B
    13% (9)
  • C
    3% (2)
  • D
    7% (5)
  • E
    75% (50)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#WBS#conceptual phase#project lifecycle#work breakdown structure