ISEB-PM1 · Question #507
Total funding requirements and periodic funding requirements are derived from:
The correct answer is D. cost baseline. Cost baseline (D) is the time-phased budget approved for the project, and both total funding requirements and periodic (e.g., quarterly) funding requirements are derived directly from it - typically the cost baseline plus management reserves equals the total funding needed…
Question
Total funding requirements and periodic funding requirements are derived from:
Options
- Afunding limit reconciliation
- Bscope baseline
- Cactivity cost estimates.
- Dcost baseline.
How the community answered
(50 responses)- A4% (2)
- B2% (1)
- C10% (5)
- D84% (42)
Explanation
Cost baseline (D) is the time-phased budget approved for the project, and both total funding requirements and periodic (e.g., quarterly) funding requirements are derived directly from it - typically the cost baseline plus management reserves equals the total funding needed, plotted over time.
Why the distractors are wrong:
- A (funding limit reconciliation) is a technique used with the cost baseline to adjust spending, not a source of funding requirements.
- B (scope baseline) defines what work is included (scope statement, WBS, WBS dictionary) but does not produce dollar figures for funding.
- C (activity cost estimates) are inputs that feed into creating the cost baseline - they're a predecessor, not the source of funding requirements.
Memory tip: Think of the cost baseline as the financial "blueprint" - just as construction funding comes from a blueprint, project funding requirements come from the cost baseline. If you see "funding requirements," go straight to D.
Topics
Community Discussion
No community discussion yet for this question.