ISEB-PM1 · Question #507

Total funding requirements and periodic funding requirements are derived from:

The correct answer is D. cost baseline. Cost baseline (D) is the time-phased budget approved for the project, and both total funding requirements and periodic (e.g., quarterly) funding requirements are derived directly from it - typically the cost baseline plus management reserves equals the total funding needed…

Project Planning

Question

Total funding requirements and periodic funding requirements are derived from:

Options

  • Afunding limit reconciliation
  • Bscope baseline
  • Cactivity cost estimates.
  • Dcost baseline.

How the community answered

(50 responses)
  • A
    4% (2)
  • B
    2% (1)
  • C
    10% (5)
  • D
    84% (42)

Explanation

Cost baseline (D) is the time-phased budget approved for the project, and both total funding requirements and periodic (e.g., quarterly) funding requirements are derived directly from it - typically the cost baseline plus management reserves equals the total funding needed, plotted over time.

Why the distractors are wrong:

  • A (funding limit reconciliation) is a technique used with the cost baseline to adjust spending, not a source of funding requirements.
  • B (scope baseline) defines what work is included (scope statement, WBS, WBS dictionary) but does not produce dollar figures for funding.
  • C (activity cost estimates) are inputs that feed into creating the cost baseline - they're a predecessor, not the source of funding requirements.

Memory tip: Think of the cost baseline as the financial "blueprint" - just as construction funding comes from a blueprint, project funding requirements come from the cost baseline. If you see "funding requirements," go straight to D.

Topics

#cost baseline#funding requirements#cost planning#funding limit reconciliation

Community Discussion

No community discussion yet for this question.