What is the status of the project whose data is shown in the following S-curve?
The correct answer is B. Over budget and behind schedule. Option B is correct because on the S-curve shown, the Actual Cost (AC) line sits above the Earned Value (EV) line - meaning more was spent than the value of work completed (Cost Performance Index < 1, over budget) - and the EV line sits below the Planned Value (PV) line…
Question
What is the status of the project whose data is shown in the following S-curve?
Options
- AUnder budget and ahead of schedule
- BOver budget and behind schedule
- COver budget and ahead of schedule
- DUnder budget and behind schedule
How the community answered
(14 responses)- A7% (1)
- B71% (10)
- C14% (2)
- D7% (1)
Explanation
Option B is correct because on the S-curve shown, the Actual Cost (AC) line sits above the Earned Value (EV) line - meaning more was spent than the value of work completed (Cost Performance Index < 1, over budget) - and the EV line sits below the Planned Value (PV) line - meaning less work was completed than planned at this point in time (Schedule Performance Index < 1, behind schedule).
Why the distractors are wrong:
- A (under budget, ahead of schedule) is the exact opposite: it would require AC below EV and EV above PV.
- C (over budget, ahead of schedule) gets the budget status right but reverses the schedule - ahead of schedule requires EV > PV, which the curve doesn't show.
- D (under budget, behind schedule) gets the schedule status right but reverses the budget - under budget requires AC < EV, which the curve doesn't show.
Memory tip: Use the "EV sandwich" rule - EV is always the middle reference line. Compare AC to EV for budget (AC above EV = over budget), and compare EV to PV for schedule (EV below PV = behind schedule). If both are unfavorable, you're in the worst quadrant: over budget and behind schedule.