ISEB-PM1 · Question #506
What does a SPI value greater than 1.0 indicate?
The correct answer is A. More work was completed than planned. SPI (Schedule Performance Index) = Earned Value (EV) ÷ Planned Value (PV). When SPI > 1.0, Earned Value exceeds Planned Value, meaning the project has completed more work than was scheduled - you're ahead of schedule. Option A is correct because a higher numerator (EV) relative…
Question
What does a SPI value greater than 1.0 indicate?
Options
- AMore work was completed than planned
- BLess work was completed than planned
- CCost overrun for completed work has occurred
- DCost underrun for completed work has occurred
How the community answered
(33 responses)- A79% (26)
- B6% (2)
- C12% (4)
- D3% (1)
Explanation
SPI (Schedule Performance Index) = Earned Value (EV) ÷ Planned Value (PV). When SPI > 1.0, Earned Value exceeds Planned Value, meaning the project has completed more work than was scheduled - you're ahead of schedule. Option A is correct because a higher numerator (EV) relative to the denominator (PV) produces a ratio above 1.
Why the distractors are wrong:
- B is the opposite - SPI < 1.0 indicates less work completed than planned (behind schedule).
- C and D both describe cost performance, which is measured by CPI (Cost Performance Index = EV/AC), not SPI. SPI is purely a schedule metric and says nothing about costs.
Memory tip: Think of SPI and CPI using the same rule - above 1.0 is good, below 1.0 is bad. For SPI specifically, remember "S = Schedule" and picture a race: SPI > 1.0 means you're ahead of the pack, SPI < 1.0 means you're behind. The letters C and D in the distractors are a trap to pull you toward cost thinking - stay in your lane (schedule).
Topics
Community Discussion
No community discussion yet for this question.