nerdexam
BCS-ISEB

ISEB-PM1 · Question #506

What does a SPI value greater than 1.0 indicate?

The correct answer is A. More work was completed than planned. SPI (Schedule Performance Index) = Earned Value (EV) ÷ Planned Value (PV). When SPI > 1.0, Earned Value exceeds Planned Value, meaning the project has completed more work than was scheduled - you're ahead of schedule. Option A is correct because a higher numerator (EV) relative…

Project Control

Question

What does a SPI value greater than 1.0 indicate?

Options

  • AMore work was completed than planned
  • BLess work was completed than planned
  • CCost overrun for completed work has occurred
  • DCost underrun for completed work has occurred

How the community answered

(33 responses)
  • A
    79% (26)
  • B
    6% (2)
  • C
    12% (4)
  • D
    3% (1)

Explanation

SPI (Schedule Performance Index) = Earned Value (EV) ÷ Planned Value (PV). When SPI > 1.0, Earned Value exceeds Planned Value, meaning the project has completed more work than was scheduled - you're ahead of schedule. Option A is correct because a higher numerator (EV) relative to the denominator (PV) produces a ratio above 1.

Why the distractors are wrong:

  • B is the opposite - SPI < 1.0 indicates less work completed than planned (behind schedule).
  • C and D both describe cost performance, which is measured by CPI (Cost Performance Index = EV/AC), not SPI. SPI is purely a schedule metric and says nothing about costs.

Memory tip: Think of SPI and CPI using the same rule - above 1.0 is good, below 1.0 is bad. For SPI specifically, remember "S = Schedule" and picture a race: SPI > 1.0 means you're ahead of the pack, SPI < 1.0 means you're behind. The letters C and D in the distractors are a trap to pull you toward cost thinking - stay in your lane (schedule).

Topics

#schedule performance index#SPI#earned value management#schedule control

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice