What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?
The correct answer is C. $140. Option C ($140) is correct because the standard PERT (Program Evaluation and Review Technique) formula for expected cost is (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6, which yields (115 + 560 + 165) ÷ 6 = 840 ÷ 6 = $140. In this case, the optimistic and pessimistic…
Question
What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?
Options
- A$115
- B$138
- C$140
- D$165
How the community answered
(25 responses)- A16% (4)
- B4% (1)
- C72% (18)
- D8% (2)
Explanation
Option C ($140) is correct because the standard PERT (Program Evaluation and Review Technique) formula for expected cost is (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6, which yields (115 + 560 + 165) ÷ 6 = 840 ÷ 6 = $140. In this case, the optimistic and pessimistic estimates are equally spread around the most likely value ($25 each), so the weighted result coincides with the most likely figure.
Why the distractors are wrong:
- A ($115) is simply the best-case (optimistic) estimate - no weighting applied.
- B ($138) doesn't result from any standard estimation formula; it may tempt test-takers who misremember the weights or miscalculate.
- D ($165) is the worst-case (pessimistic) estimate - again, no formula applied.
Memory tip: Think of PERT as "1-4-1" - the most likely estimate gets 4 votes, while optimistic and pessimistic each get 1 vote, all divided by 6. This reflects real-world logic: the most experienced estimate deserves the most weight.