ISEB-PM1 · Question #505

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

The correct answer is C. $140. Option C ($140) is correct because the standard PERT (Program Evaluation and Review Technique) formula for expected cost is (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6, which yields (115 + 560 + 165) ÷ 6 = 840 ÷ 6 = $140. In this case, the optimistic and pessimistic…

Project Planning

Question

What is the expected activity cost for a project having a most likely cost of $140, a best case scenario of $115, and a worst case scenario of $165?

Options

  • A$115
  • B$138
  • C$140
  • D$165

How the community answered

(25 responses)
  • A
    16% (4)
  • B
    4% (1)
  • C
    72% (18)
  • D
    8% (2)

Explanation

Option C ($140) is correct because the standard PERT (Program Evaluation and Review Technique) formula for expected cost is (Optimistic + 4 × Most Likely + Pessimistic) ÷ 6, which yields (115 + 560 + 165) ÷ 6 = 840 ÷ 6 = $140. In this case, the optimistic and pessimistic estimates are equally spread around the most likely value ($25 each), so the weighted result coincides with the most likely figure.

Why the distractors are wrong:

  • A ($115) is simply the best-case (optimistic) estimate - no weighting applied.
  • B ($138) doesn't result from any standard estimation formula; it may tempt test-takers who misremember the weights or miscalculate.
  • D ($165) is the worst-case (pessimistic) estimate - again, no formula applied.

Memory tip: Think of PERT as "1-4-1" - the most likely estimate gets 4 votes, while optimistic and pessimistic each get 1 vote, all divided by 6. This reflects real-world logic: the most experienced estimate deserves the most weight.

Topics

#PERT#expected activity cost#three-point estimating#cost estimation