ISEB-PM1 · Question #22

The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?

The correct answer is A. Update resource requirements. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?

Options

  • AUpdate resource requirements
  • BRecommend corrective actions
  • CEstimate Activity Durations
  • DCreate a milestone list

How the community answered

(58 responses)
  • A
    79% (46)
  • B
    12% (7)
  • C
    3% (2)
  • D
    5% (3)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#schedule network analysis#Monte Carlo analysis#schedule compression#resource requirements

Community Discussion

No community discussion yet for this question.