ISEB-PM1 · Question #22
The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?
The correct answer is A. Update resource requirements. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?
Options
- AUpdate resource requirements
- BRecommend corrective actions
- CEstimate Activity Durations
- DCreate a milestone list
How the community answered
(58 responses)- A79% (46)
- B12% (7)
- C3% (2)
- D5% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule network analysis#Monte Carlo analysis#schedule compression#resource requirements