Question

The project manager has performed schedule network analysis, compressed the schedule, and completed a Monte Carlo analysis. What time management activity should be done NEXT?

Options

  • AUpdate resource requirements
  • BRecommend corrective actions
  • CEstimate Activity Durations
  • DCreate a milestone list