BCS-ISEB
ISEB-PM1 · Question #21
ISEB ISEB-PM1 Exam A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
The correct answer is B. Schedule compression. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
ISEB ISEB-PM1 Exam A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?
Options
- AResource leveling
- BSchedule compression
- CCritical chain
- DAdjusting leads and lags
How the community answered
(42 responses)- A7% (3)
- B79% (33)
- C12% (5)
- D2% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule compression#crashing#cost-time tradeoff#schedule management
Community Discussion
No community discussion yet for this question.