ISEB ISEB-PM1 Exam A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?

The correct answer is B. Schedule compression. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

ISEB ISEB-PM1 Exam A project manager has increased project costs by US $100,000, but completed the project four weeks earlier than planned. What activity is BEST described here?

Options

  • AResource leveling
  • BSchedule compression
  • CCritical chain
  • DAdjusting leads and lags

How the community answered

(42 responses)
  • A
    7% (3)
  • B
    79% (33)
  • C
    12% (5)
  • D
    2% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#schedule compression#crashing#cost-time tradeoff#schedule management