An activity-on-node (AON) network diagram shows the following activities on two critical paths; Start, D, E, J, L, End and Start, D, E, G, I, L, End. Each activity is at least three days in…
The correct answer is D. Activity D or activity E. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
An activity-on-node (AON) network diagram shows the following activities on two critical paths; Start, D, E, J, L, End and Start, D, E, G, I, L, End. Each activity is at least three days in duration, except for activity L, which is one day in duration. If you are directed to reduce the project by one day, which activities are MOST likely to change?
Options
- AActivity L
- BActivity E or activity J
- CActivity G or activity I
- DActivity D or activity E
How the community answered
(66 responses)- A18% (12)
- B5% (3)
- C8% (5)
- D70% (46)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#critical path compression#schedule compression#float#network diagram