A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and…

The correct answer is A. Activity A has two weeks float, activity F has one week. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?

Options

  • AActivity A has two weeks float, activity F has one week.
  • BActivity F has one week float.
  • CThere is no float available in the project.
  • DActivity A has eight weeks float.

How the community answered

(39 responses)
  • A
    82% (32)
  • B
    10% (4)
  • C
    3% (1)
  • D
    5% (2)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#float calculation#critical path#network diagram#schedule analysis