ISEB-PM1 · Question #19
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and…
The correct answer is A. Activity A has two weeks float, activity F has one week. You've hit your session limit · resets 10:20pm (America/New_York)
Question
A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, Activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as Activity C is completed. Activity E must be completed before Activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?
Options
- AActivity A has two weeks float, activity F has one week.
- BActivity F has one week float.
- CThere is no float available in the project.
- DActivity A has eight weeks float.
How the community answered
(39 responses)- A82% (32)
- B10% (4)
- C3% (1)
- D5% (2)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)