If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?
The correct answer is C. Perform resource leveling. You've hit your session limit · resets 10:20pm (America/New_York)
Resource Management
Question
If project time and cost are not as important as the number of resources used each month, which of the following is the BEST thing to do?
Options
- APerform a Monte Carlo analysis.
- BFast track the project.
- CPerform resource leveling.
- DAnalyze the life cycle costs.
How the community answered
(22 responses)- A5% (1)
- B18% (4)
- C73% (16)
- D5% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#resource leveling#resource constraints#schedule optimization