ISEB-PM1 · Question #181
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?
The correct answer is D. Planning. Planning (D) is correct because gathering requirements and creating estimates are core Planning process group activities - this is where the project scope, schedule, and cost baselines are defined before work begins. Initiating (B) is wrong because that group focuses on…
Question
You are a project manager working on gathering requirements and establishing estimates for the project. Which process group are you in?
Options
- AMonitoring and Controlling
- BInitiating
- CExecuting
- DPlanning
How the community answered
(39 responses)- A8% (3)
- B5% (2)
- C13% (5)
- D74% (29)
Explanation
Planning (D) is correct because gathering requirements and creating estimates are core Planning process group activities - this is where the project scope, schedule, and cost baselines are defined before work begins.
Initiating (B) is wrong because that group focuses on authorizing the project and identifying stakeholders, not the detailed work of collecting requirements. Executing (C) is where the actual project work is carried out according to the plan, not where the plan is built. Monitoring and Controlling (A) happens throughout the project but is about tracking performance and managing changes, not establishing estimates.
Memory tip: Think of the process groups in order - Instantly Plan before Executing, then Monitor, and finally Close (Initiating → Planning → Executing → Monitoring & Controlling → Closing). Any question mentioning "gathering," "defining," "estimating," or "establishing" points squarely to Planning.