CAPM Question #8: Real Exam Question with Answer & Explanation
The correct answer is C: Project management plan, project documents, and organizational process assets. See the full explanation below for the reasoning.
Predictive, Plan-Based Methodologies
Question
Which are inputs for the Plan Quality Management process?
Options
- AQuality metrics, project documents, and financial performance
- BQuality management plan, project documents, and quality metrics
- CProject management plan, project documents, and organizational process assets
- DProject management plan, quality metrics, and project documents
Topics
#Plan Quality Management#PMBOK Processes#Inputs#Project Management Plan