Which are inputs for the Plan Quality Management process?

The correct answer is C. Project management plan, project documents, and organizational process assets. According to the PMBOK Guide, the inputs to the Plan Quality Management process are: Project Charter, Project Management Plan (including scope, schedule, and risk management plan), Project Documents (e.g., assumption log, requirements documentation, stakeholder register)…

Predictive, Plan-Based Methodologies

Question

Which are inputs for the Plan Quality Management process?

Options

  • AQuality metrics, project documents, and financial performance
  • BQuality management plan, project documents, and quality metrics
  • CProject management plan, project documents, and organizational process assets
  • DProject management plan, quality metrics, and project documents

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    89% (32)
  • D
    6% (2)

Explanation

According to the PMBOK Guide, the inputs to the Plan Quality Management process are: Project Charter, Project Management Plan (including scope, schedule, and risk management plan), Project Documents (e.g., assumption log, requirements documentation, stakeholder register), Enterprise Environmental Factors, and Organizational Process Assets. Quality metrics and the Quality Management Plan are outputs of this process, not inputs - so any option listing them as inputs is incorrect. Option C correctly identifies inputs without including outputs.