nerdexam
PMIPMI

CAPM · Question #532

CAPM Question #532: Real Exam Question with Answer & Explanation

The correct answer is D: Prototyping. See the full explanation below for the reasoning.

Business Analysis Frameworks

Question

A business analyst is in the process of eliciting requirements. The stakeholders have struggled to convey the features they want in the product. The development team is schedule-constrained, however, and wants the requirements sooner than later. Which of the following should help with this situation?

Options

  • AInterviews
  • BWorkshops
  • CBrainstorming
  • DPrototyping

Topics

#Requirements Elicitation#Prototyping#Business Analysis Tools#Stakeholder Engagement

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions