PMIPMI
CAPM · Question #532
CAPM Question #532: Real Exam Question with Answer & Explanation
The correct answer is D: Prototyping. See the full explanation below for the reasoning.
Business Analysis Frameworks
Question
A business analyst is in the process of eliciting requirements. The stakeholders have struggled to convey the features they want in the product. The development team is schedule-constrained, however, and wants the requirements sooner than later. Which of the following should help with this situation?
Options
- AInterviews
- BWorkshops
- CBrainstorming
- DPrototyping
Topics
#Requirements Elicitation#Prototyping#Business Analysis Tools#Stakeholder Engagement
Community Discussion
No community discussion yet for this question.