CAPM · Question #531

During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

The correct answer is A. Project team charter. The Project Team Charter (also called a Team Charter or Working Agreement) is the document that captures how the team agrees to work together, including ground rules for communication, conflict resolution, and - critically - decision-making approaches. When team members cannot…

Project Management Fundamentals and Core Concepts

Question

During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

Options

  • AProject team charter
  • BProject management plan
  • CProject team assignments
  • DProject issue log

How the community answered

(36 responses)
  • A
    92% (33)
  • B
    6% (2)
  • D
    3% (1)

Explanation

The Project Team Charter (also called a Team Charter or Working Agreement) is the document that captures how the team agrees to work together, including ground rules for communication, conflict resolution, and - critically - decision-making approaches. When team members cannot agree on how to make decisions, the Team Charter is the reference document. The project management plan covers the broader project approach, team assignments list who is on the project, and the issue log tracks problems - none govern internal team operating agreements.

Topics

#Project team charter#Team decision-making#Team management#Project documents