CAPM Question #531: Real Exam Question with Answer & Explanation

The correct answer is A: Project team charter. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

Options

  • AProject team charter
  • BProject management plan
  • CProject team assignments
  • DProject issue log

Topics

#Project team charter#Team decision-making#Team management#Project documents