During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

Sign in or unlock CAPM to reveal the answer and full explanation for question #531. The question stem and answer options stay visible for context.

Project Management Fundamentals and Core Concepts

Question

During execution of a project, a team could not reach consensus on the decision-making approach. Which document should the team member refer to?

Options

  • AProject team charter
  • BProject management plan
  • CProject team assignments
  • DProject issue log